ATTACHMENT G

   REQUIREMENTS FOR DISCHARGERS WHO HAVE BEEN GRANTED AN
              OCEAN PLAN EXCEPTION FOR DISCHARGES TO ASBS

    quality in the affected ASBS. The ASBS Compliance Plan shall include a
    description of appropriate non-structural controls and a time schedule to
    implement structural controls (implementation schedule) to comply with these
    special conditions for inclusion in the Discharger’s SWPPP.

3. By September 20, 2014, the Discharger shall submit the final ASBS Compliance
    Plan, including a description and final schedule for structural controls based on
    the results of runoff and receiving water monitoring.

4. By September 20, 2013, any non-structural controls that are necessary to comply
    with these special conditions shall be implemented.

5. By March 20, 2018, any structural controls identified in the ASBS Compliance
    Plan that are necessary to comply with these special conditions shall be
    operational.

6. By March 20, 2018, all Dischargers must comply with the requirement that their
    discharges into the affected ASBS maintain natural ocean water quality. If the
    initial results of post-storm receiving water quality testing indicate levels higher
    than the 85th percentile threshold of reference water quality data and the pre-
    storm receiving water levels, then the Discharger must re-sample the receiving
    water, pre- and post-storm. If after re-sampling the post-storm levels are still
    higher than the 85th percentile threshold of reference water quality data, and the
    pre-storm receiving water levels, for any constituent, then natural ocean water
    quality is exceeded. See Flowchart at the end of this Attachment.

7. The Executive Director may only authorize additional time to comply with the
    special conditions 5 and 6, above if good cause exists to do so. Good cause
    means a physical impossibility or lack of funding

    If a Discharger claims physical impossibility, it shall notify the Board in writing
    within thirty (30) days of the date that the Discharger first knew of the event or
    circumstance that caused or would cause it to fail to meet the deadline in 5. or 6.
    The notice shall describe the reason for the noncompliance or anticipated
    noncompliance and specifically refer to this Section of these requirements. It
    shall describe the anticipated length of time the delay in compliance may persist,
    the cause or causes of the delay as well as measures to minimize the impact of
    the delay on water quality, the measures taken or to be taken by the Discharger
    to prevent or minimize the delay, the schedule by which the measures will be
    implemented, and the anticipated date of compliance. The Discharger shall
    adopt all reasonable measures to avoid and minimize such delays and their
    impact on water quality.

    The Discharger may request an extension of time for compliance based on lack
    of funding. The request for an extension shall require:

Order 2014-0057-DWQ  5