Linear Infrstructure Permitting Exemptions
Exemptions and Exclusions for Permitting Linear Infrastructure Projects

Environmental permitting can be challenging for large-scale linear infrastructure installation or repair projects that span multiple agency jurisdictions. Projects such as gas and electric transmission lines, telecommunications lines, water and sewer pipelines, and transportation corridors often serve regional public needs, but their geographic scale and length can increase environmental and permitting complexity. Long linear infrastructure projects often cross multiple regulatory authorities, each with distinct permitting requirements or interpretations. Without early environmental planning, permitting can become time-consuming, costly, and prone to unanticipated delays.

However, many linear infrastructure projects have opportunities to reduce permitting burdens. Projects that consider environmental constraints during the routing and design stages may be able to largely avoid sensitive resources. When avoidance is not feasible, many federal, state, and local regulatory frameworks offer exemptions, exclusions, or exception-based reviews intended to streamline approvals for low-impact utility projects. By understanding and applying these pathways early in the planning process, project teams can reduce review timelines, maintain regulatory compliance, and keep schedules and budgets on track.

This Delve explores the most relevant exemptions and exclusions available to linear infrastructure projects, when they apply, and how agencies interpret them in practice.

Predictable Disturbance Patterns 

Unlike facility-based development, linear infrastructure projects typically result in narrow, continuous, and predictable areas of disturbance. Work often occurs within existing corridors such as roadways, utility easements, and transmission rights-of-way (ROWs), where environmental conditions are already documented, and impacts can be effectively managed. Federal regulations, including the National Environmental Policy Act (NEPA) and the Clean Water Act (CWA), recognize this pattern and provide exclusions or expedited pathways for minor utility construction, maintenance, and upgrades. As a result, the permitting process for linear projects often depends less on whether the project qualifies for an exemption or exclusion and more on whether individual activities or segments meet specific eligibility criteria.  

Is NEPA Triggered?  

A key early question for any linear project is whether NEPA applies to the construction and implementation of the proposed design. NEPA is triggered only when a federal nexus exists, such as the use of federal land, receipt of federal funding, or the need for a federal permit.

When NEPA applies, many linear activities may still qualify for established Categorical Exclusions (CEs). A CE applies when environmental impacts are expected to be minimal, allowing agencies to forgo preparation of a more detailed Environmental Assessment (EA) or Environmental Impact Statement (EIS). 

Examples include:

  • National Telecommunications and Information Administration categorical exclusion for installation of utility and communication systems within existing ROWs (89 FR 22688)
  • U.S. Forest Service categorical exclusion for approving the use of land for a utility corridor that crosses a national forest (36 CFR 220.6(e)(3))
  • Federal Highway Administration categorical exclusion for utility installations along or across transportation corridors (23 CFR 771.117(c)(2)) 

Some federal programs complete NEPA review at a programmatic level. For example, the U.S. Army Corps of Engineers (USACE) Nationwide Permits (NWPs), including NWP 12 for Utility Line Activities, rely on NEPA analyses completed during rulemaking. When a project qualifies for an NWP, USACE does not typically require additional project-specific NEPA documentation. Applicants must still comply with applicable general and regional conditions, but the overall NEPA review burden is significantly reduced. 

Resource Considerations  

Even when exemptions or exclusions are available agencies still require documentation demonstrating that sensitive resources have been adequately evaluated. Biological resources remain a common trigger for additional review. Eligibility for an exemption or exclusion typically requires that no listed species, designated critical habitat, or nesting or breeding sites will be affected. For hydrological resources, linear projects often cross wetlands, streams, or ephemeral drainages, and maintaining eligibility depends on impact thresholds, crossing methods, and cumulative effects. Cultural resources should also be evaluated early, as linear projects increase the likelihood of intersecting historic or archaeological sites that may require further review by the State Historic Preservation Office (SHPO) and potential design modifications to avoid impacts. Formal SHPO coordination is required for all projects with a federal nexus, in accordance with Section 106 of the National Historic Preservation Act.

In addition to federal resource protections, states and local agencies may impose additional regulatory requirements. Potential impacts to these resources can often be minimized through thoughtful project design, construction methodologies, and timing considerations.

Pitfalls and Early Coordination  

Projects may lose exemption or exclusion eligibility when new ground disturbance or significant project changes are added late in the review process. Cumulative impacts can also pose challenges, for example, when multiple small wetland crossings collectively exceed allowable thresholds. Additionally, previously unknown sensitive biological or cultural resources identified after route selection can delay review and jeopardize streamlined permitting pathways.

Early, proactive coordination with agencies, land managers, tribes, and other stakeholders is one of the most effective ways to minimize these risks. Confirming eligibility criteria early helps establish clear expectations for surveys and documentation, provides regulatory predictability, and supports streamlined permitting throughout the project lifecycle.

Have Questions?  

Our team will discuss these topics in greater depth in our upcoming webinar on April 15, 2026, including recent case studies and practical permitting strategies for utility owners and developers.  

In the meantime, if you have questions about permitting and environmental compliance for linear infrastructure projects, Trihydro’s environmental specialists are available to help. 

Contact Us

Kira Becker
Kira Becker
Environmental Compliance and Permitting Specialist, San Luis Obispo, CA

Ms. Becker is an environmental compliance and permitting specialist with experience supporting remediation, restoration, and linear utility projects. Her focus is on Endangered Species Act and Clean Water Act compliance. Her work includes coordinating with regulatory agencies, preparing permitting documentation, and supporting environmental review.

Did you find this information useful? Click the icons below to share on your social channels.


facebook twitter linkedin
Other News

SIGN UP FOR INDUSTRY NEWS

Receive the latest technical and regulatory updates in your inbox.